PERT Diagrams (network diagrams)
PERT diagrams or critical path networks use a graphical form to show relationships between activities and time frames.
Part of a PERT diagram. Notice that for each event start and finish dates are included.
They differ from GANTT charts in that they are better at identifying the relationship between tasks rather than the progress of tasks over time.
Key elements in developing a PERT diagram:
Activities - list of activities in the project and their dependencies
Nodes/Events - indicating the beginning or end of an activity
Network lines show the interdependence of events
Indication of the critical path - the sequence of dependent events that have the sum of longest duration
Indication of slack time - events not on the critical path usually have slack time, extra time for that event that does not effect the timing of other events thus not effecting the project time. That means that can fall behind schedule and there is no impact on the project completion date.