Information Technology - Project Management Tools

Project Managment Tools

This resource covers the tools used by a Project Manager beginning with
'GANTT' charts.

A project plan is often constructed within the planning phase. It contains
all activities and milestones. These events are placed in a particular time
sequence, ultimately producing something similar to a horizontal bar chart.

A GANTT chart displays tasks and costs along a horizontal time scale, much
like a calendar. The time for each task is recorded, by indicating the
start and finish dates. It should show the best possible way to complete
the project in the shortest time. Activities can be done in parallel or
sequentially, and the GANTT chart shows this clearly. Even though it lists
tasks, it does not show the critical path as there is no indication of the
relationship between tasks.

From this GANTT chart you can find out the following,Image.

Activity 3.0.2 Production Build:

* Has a duration of 10 days

* Must be done after Order Production Materials and Final Code Release

* Must be done before Ship Product

* Is expected to start 6/8/99 (mm/dd/yy)

* Is expected to finish 6/21/99 (mm/dd/yy)

* Is on the critical path (indicated in red)