Sign-up today to join over 3 million learners already on ALISON:

ALISON: Diploma in Project Management

Questions & Answers about Project management toolset - Scheduling and expediting

The Question must be about:
- Module: Project management toolset
- Topic: Scheduling and expediting

Latest Questions

  • George Fragos Greece who else can be on duty, except project manager and who decide about this?
    2014-08-30 15:08:47

  • Ajayi Folake Nigeria i dnt understand scheduling and expediting,pls explain. if i can get detail explanation in my box. folak_ajayi@yahoo.com
    2014-08-21 11:08:40

    • Yai Deng Yai South Sudan Just read the summary text above before you answere questions.
      2014-08-24 13:08:15
  • Je Rouse United Kingdom when scheduling the project, is it best to build in some contingency in case the contractor take longer that originaly planned?
    2014-08-07 15:08:21

    • George Fragos Greece I think it is depending on what the contractor is..
      2014-08-30 15:08:44
    • Yai Deng Yai South Sudan That is usually possible for the success of the project.
      2014-08-24 13:08:11
    • Glen Holmes Ireland Yes this is usually inevitable but you would usually consider putting penalties in place that a contractor would occur if they don't deliver on time.
      2014-08-15 21:08:21
  • WAYNE MUNSON United Kingdom Do you provide any information on the completion of a schedule of works as this would detail all of the above
    2014-08-03 09:08:10

    • Yai Deng Yai South Sudan Yes there is always reports being submitted through out project implementation period.
      2014-08-24 13:08:25
  • Samuel Kofi Odoi Ghana This really indicates that time of working during a project outline is important and must be respected.
    2014-07-26 05:07:41

  • Janvier Nyandamu Rwanda Time and cost! are these two parameters the only parameters in scheduling and expediting?
    2014-07-22 17:07:05

    • Yai Deng Yai South Sudan And also the policies.
      2014-08-24 13:08:34
    • Samuel Kofi Odoi Ghana Note that process of expediting a project may cost extra money, however time should also be adjusted.
      2014-07-26 05:07:33
  • Vikram Vasant Rotkar United Kingdom What to be expedited during the project brief?
    2014-07-21 15:07:19

    • Yai Deng Yai South Sudan Cost and timeframe.
      2014-08-24 13:08:08
    • Samuel Kofi Odoi Ghana Expediting the project to meet the time constrained either by the manager or the board members of the project.
      2014-07-26 05:07:32
  • Jones Hanungu Munang'andu Zambia Management Both during and after World War II the United States operated the largest and most advanced logistic system in the world. Its wartime operations stressed speed, volume, and risk-taking more than efficiency and economy. The postwar years, with accelerated technological change, skyrocketing costs, and diminished public interest in defense, brought a revulsion against military prodigality, manifested by calls for reduced defense budgets and a growing demand for more efficient management of the military establishment. This demand culminated in a thorough overhaul of the whole system in the 1960s. One result was the reorganization of logistic activities in the three military services, generally along functional lines, with large logistic commands operating under functional staff supervision. In each service, however, each major weapon system was centrally managed by a separate project officer, and central inventory control was maintained for large commodity groups. In 1961 a new defense supply agency was established to manage on a wholesale basis the procurement, storage, and distribution of common military supplies and the administration of certain common services. The most far-reaching managerial reforms of the period were instituted by the U.S. defense secretary, Robert S. McNamara (1961–68), in the resource allocation process. A unified defense planning–programming–budgeting system provided for five-year projections of force, manpower, and dollar requirements for all defense activities, classified into eight or nine major programs (such as strategic forces) that cut across the lines of traditional service responsibilities. The system was introduced in other federal departments after 1965, and elements of it were adopted by the British and other governments. In 1966 a program was inaugurated to integrate management accounting at the operating level with the programming–budgeting system. At the end of the 1960s a new administration restored some of the initiative in the planning–budgeting–programming cycle to the Joint Chiefs of Staff and the military services. The reforms of the 1960s exploited the whole range of current managerial methodology. The basic techniques, such as systems and operations analysis, all stressed precise, scientific, usually quantitative formulations of problems and mathematical approaches to rational decision making. Systems analysis, the technique associated with defense planning and programming, was a method of economic and mathematical analysis useful in dealing with complex problems of choice under conditions of uncertainty. The technological foundation of this improved logistic management was the high-speed electronic computer, which was being used chiefly in inventory control; in automated operations at depots, bases, and stations; in transmitting and processing supply data; in personnel administration; and in command-and-control networks.
    2014-07-17 20:07:41

  • Gregory Ngene Nigeria SO IT MEANS THAT TIME AND COSTS MUST BE TRADED OFF IN ODER TO COMPLETE THE PROJECT
    2014-07-08 10:07:04

    • Yai Deng Yai South Sudan Absolutely.
      2014-08-24 13:08:00
  • Daniel Chol Koknyin South Sudan After a project manager made assessment by use of critical path method and later on gets some difficulties that leads to crash of the project, does it means that he/she has to go back at planning and designing stages or what can a manager do?
    2014-07-04 13:07:07

    • Yai Deng Yai South Sudan He/she can make some adjustment through expediting.
      2014-08-24 13:08:03
  • Chika Ejiofor Nigeria When confronted with a change in planned activities on field, is it better to take immediate actions or expand on options to choose the most favourable line of action? The latter more often than not would take more time. If actions are taken spur of the moment that leads to costly mistakes, what can the Project Manager do to damage control such mistakes already made without getting into problems with the management or team members ?
    2014-07-02 11:07:00

    • Yai Deng Yai South Sudan He/ she can always be monitoring the progress of the work any deviation can be correceted as earlier as possible.
      2014-08-24 13:08:56
  • Reza Abbasi Iran Who has the duty to assess the various stages of project scheduling?
    2014-06-22 15:06:22

    • Yai Deng Yai South Sudan Project Manager.
      2014-08-24 13:08:15
    • ODAFE PATRICK OHWOJERO Nigeria the project manager has the duty
      2014-06-23 10:06:45
  • Reza Abbasi Iran Who has the duty to assess the various stages of project scheduling?
    2014-06-19 20:06:07

    • Ko Ko Oo Singapore the project manager has the duty
      2014-06-27 10:06:07
  • Reza Abbasi Iran It is high or low speed operation in a project?
    2014-06-19 20:06:46

    • Yai Deng Yai South Sudan Both depend on the what management agreed.
      2014-08-24 13:08:13
    • Ko Ko Oo Singapore high speed
      2014-06-27 10:06:18
  • Reza Abbasi Iran Whether the project is done exactly according to the original schedule?
    2014-06-19 20:06:45

    • Yai Deng Yai South Sudan Is by Monitoring and Evaluation.
      2014-08-24 13:08:59
    • Ko Ko Oo Singapore sometime will be change the original schedule
      2014-06-27 10:06:22
  • Satu Korhonen Finland What are the three aspects that need to be considered when the project is delayed
    2014-06-16 10:06:26

    • Yai Deng Yai South Sudan Time Cost Project staff skills.
      2014-08-24 13:08:41
    • Reza Abbasi Iran resources, time or money
      2014-06-19 20:06:17
    • ojo taiwo Nigeria alternate action[s], time and cost
      2014-06-19 13:06:26
    • Parhalad Saini India resources, time or money are aspects need when the project is delayed.
      2014-06-17 09:06:43
  • Annette Weizbauer Germany When is it worth considering if it is worth spending money and effort for saving time?
    2014-06-14 10:06:15

    • Yai Deng Yai South Sudan It is when expediting.
      2014-08-24 13:08:33
    • ojo taiwo Nigeria when a task in a project is not nearing completion at the stated time and in the judgement of the PM after due consideration extra effort and time will enable the delivery of the project at the estimated time
      2014-06-19 13:06:08
    • Poliect Chuwa Tanzania When considering to crash an activity
      2014-06-16 02:06:36
    • Poliect Chuwa Tanzania When crashing an activity
      2014-06-16 02:06:57
    • Okwuchukwu Akabogu Nigeria When the basic success criteria in the project is the time factor. That is, when the ultimate aim of the project is to deliver within scheduled time.
      2014-06-14 10:06:23
  • Annette Weizbauer Germany Which tasks have to be identified during the phase of schedule and expediting ?
    2014-06-13 16:06:18

    • Reza Abbasi Iran Project Manager
      2014-06-19 20:06:25
    • ojo taiwo Nigeria all tasks but more importantly those that are not on the critical path
      2014-06-19 13:06:01
    • Satu Korhonen Finland All tasks should be identified if realistic resources are to be brought to the project
      2014-06-16 10:06:54
    • Poliect Chuwa Tanzania Tasks that are on critical path
      2014-06-16 03:06:07
    • Okwuchukwu Akabogu Nigeria Those tasks that can be hastened with more money or effort.
      2014-06-14 10:06:25
Loading Menu